The Reserve at the Bear Lake-Water Line and Road Project

CSG was tasked to design a 12” water line to provide water to the Reserve at the Lake project. The design
of the 12” water line consisted of 1.5 miles of 12” water line and the construction of a new roadway along
the water line alignment. The water line presented unique challenges with four different pressure zones
due to the elevation drop across the 1.5 mile roadway. The roadway also had unique challenges with the
slope of the roadway not exceeding 8 percent. This required a large amount of cut/fill to construct the
roadway. The roadway and water line were completed in the Fall of 2014.

Services Provided:

  • Conceptual Planning
  • Water Modeling of Overall Reserve Water System
  • DEQ Entitlements
  • Civil Construction Drawings
  • Construction Staking
  • Construction Inspections